BC-PRJ-002 · Commercial Construction

Commercial Building – Edappally

GreenLeaf Properties Pvt Ltd · Edappally, Ernakulam · PM Vivek Thomas · Site Arun Raj

Ongoing
Revised Contract
₹1.80 Cr
Actual Cost
₹94.0 L
Forecast Profit
₹32.0 L
Forecast Margin
17.8%
Outstanding
₹18.0 L
Open QA/HSE issues
0

Progress

Actual 65%Planned 65%
Foundation
100%
RCC
100%
Masonry
100%
Flooring
100%
Electrical
100%
Plumbing
20%
Painting
0%
Miscellaneous
0%

Project Details

Start
15/01/2026
Finish
31/03/2027
Client
GreenLeaf Properties Pvt Ltd
Area
7,200 Sq.ft
Estimated Cost
₹1,48,00,000
BOQ value
₹1,48,00,000
Latest DPR
16/11/2026
Contract
CT-BC-PRJ-002
Original Contract
₹1.80 Cr
Approved Variations
₹0
Revised Contract Value
₹1.80 Cr
Revised Budget
₹1.48 Cr
Original est. ₹1.48 Cr
Actual Cost Incurred
₹94.0 L
64% of budget · 65% done
Forecast Cost to Complete
₹54.0 L
Forecast Cost at Completion
₹1.48 Cr
Forecast Gross Profit
₹32.0 L
Forecast Gross Margin
17.8%
Estimated 17.8%
Invoiced
₹1.26 Cr
Received
₹1.08 Cr
Outstanding
₹18.0 L
₹18.0 L client receivable outstanding.

Budget vs Actual by Cost Category

Actual Cost Composition

Revised Contract = Original + Approved Variations · Forecast at Completion = Actual + Forecast to Complete · Forecast Profit = Revised Contract − Forecast at Completion. Actual cost uses material consumption, not purchases, to avoid double counting.