BC-PRJ-005 · Commercial Interior
Commercial Interior – Ernakulam
UrbanNest Retail · Ernakulam, Kerala · PM Divya Pillai · Site Arun Raj
Planning
Revised Contract
₹42.0 L
Actual Cost
₹0
Forecast Profit
₹9.0 L
Forecast Margin
21.4%
Outstanding
₹0
Open QA/HSE issues
0
Progress
Actual 0%Planned 0%
Foundation
0%
RCC
0%
Masonry
0%
Flooring
0%
Electrical
0%
Plumbing
0%
Painting
0%
Miscellaneous
0%
Project Details
Start
01/12/2026
Finish
30/04/2027
Client
UrbanNest Retail
Area
2,600 Sq.ft
Estimated Cost
₹33,00,000
BOQ value
₹33,00,000
Latest DPR
—
Contract
CT-BC-PRJ-005
Original Contract
₹42.0 L
Approved Variations
₹0
Revised Contract Value
₹42.0 L
Revised Budget
₹33.0 L
Original est. ₹33.0 L
Actual Cost Incurred
₹0
0% of budget · 0% done
Forecast Cost to Complete
₹33.0 L
Forecast Cost at Completion
₹33.0 L
Forecast Gross Profit
₹9.0 L
Forecast Gross Margin
21.4%
Estimated 21.4%
Invoiced
₹0
Received
₹0
Outstanding
₹0
Budget vs Actual by Cost Category
Actual Cost Composition
Revised Contract = Original + Approved Variations · Forecast at Completion = Actual + Forecast to Complete · Forecast Profit = Revised Contract − Forecast at Completion. Actual cost uses material consumption, not purchases, to avoid double counting.