Estimation
Estimates & BOQ
Residential Renovation – Thrissur · Project → Work Category → Item
Approved
BOQ Total
₹22.0 L
8 items
Material
₹13.2 L
Labour
₹5.5 L
Equipment
₹3.3 L
Cost / Sq.ft
₹1,222
1,800 Sq.ft
Approved Budget vs Actual Cost
| Cost type | Budget | Actual | Remaining / variance | % |
|---|---|---|---|---|
| Material | ₹13,20,000 | ₹3,60,000 | ₹9,60,000 | 72.7% |
| Labour | ₹5,50,000 | ₹1,50,000 | ₹4,00,000 | 72.7% |
| Other | ₹3,30,000 | ₹90,000 | ₹2,40,000 | 72.7% |
| Item Code | Room | Description | Unit | Qty | Material | Labour | Equip. | Unit Cost | Amount | |
|---|---|---|---|---|---|---|---|---|---|---|
| Foundation | ₹3,30,000 | |||||||||
| BC-PRJ-003-1 | General | Lump Sum | ₹3,30,000 | ₹3,30,000 | ||||||
| RCC | ₹5,50,000 | |||||||||
| BC-PRJ-003-2 | General | Lump Sum | ₹5,50,000 | ₹5,50,000 | ||||||
| Masonry | ₹3,30,000 | |||||||||
| BC-PRJ-003-3 | General | Lump Sum | ₹3,30,000 | ₹3,30,000 | ||||||
| Flooring | ₹2,64,000 | |||||||||
| BC-PRJ-003-4 | General | Lump Sum | ₹2,64,000 | ₹2,64,000 | ||||||
| Electrical | ₹2,20,000 | |||||||||
| BC-PRJ-003-5 | General | Lump Sum | ₹2,20,000 | ₹2,20,000 | ||||||
| Plumbing | ₹1,76,000 | |||||||||
| BC-PRJ-003-6 | General | Lump Sum | ₹1,76,000 | ₹1,76,000 | ||||||
| Painting | ₹2,20,000 | |||||||||
| BC-PRJ-003-7 | General | Lump Sum | ₹2,20,000 | ₹2,20,000 | ||||||
| Miscellaneous | ₹1,10,000 | |||||||||
| BC-PRJ-003-8 | General | Lump Sum | ₹1,10,000 | ₹1,10,000 | ||||||
| Total BOQ Amount | ₹22,00,000 | |||||||||
Total Unit Cost = Material + Labour + Equipment rate · Amount = Quantity × Total Unit Cost